Peterborough Regional Airport Taxiway Bravo Construction

Taxiway Bravo Construction

Construction of the Taxiway Bravo extension project commenced on June 1, 2026 at Peterborough Airport.

The project includes the construction of an approximately 1,500-foot extension of Taxiway Bravo to the west. The western extent of the taxiway will include a holding bay designed to accommodate Code B aircraft, with wingspans up to 23.9 metres. The project will improve aircraft movement efficiency, improve capacity, and support future airside development.

During construction, pilots should expect temporary operational impacts, including changes to available runway length, declared distances, taxi routes, lighting availability, and access to portions of the airfield. 

Construction Timeline: June to October 2026

Construction is expected to occur from June to October 2026. Throughout the construction period, the available length of Runway 09-27 will be reduced.

  • THR 09 DISPLACED BY 1,102FT
  • FIRST 1,102FT RWY 09 CLSD
  • WITH RWY 09/27 SHORTENED, DECLARED DIST CHANGED TO:
  • RWY 09  TORA 5903  TODA 6198  ASDA 5903  LDA 5903
  • RWY 27  TORA 5903  TODA 5903  ASDA 5903  LDA 5294

July 6 to July 19, 2026

During this period, declared distances of Runway 09-27 will be further reduced to accommodate connection of the taxiway to the primary runway. 

  • FIRST 3,072 FT RWY09 CLSD DUE CONST.
  • WITH RWY 09/27 SHORTENED, DECLARED DIST CHANGED TO:
  • RWY 09 TORA 3933 TODA 4228 ASDA 3933 LDA 3933
  • RWY 27 TORA 3933 TODA 3933 ASDA 3933 LDA 3324

Please ensure that you check NOTAM prior to each flight. For more information, review the Construction Notice, visit the Connect Peterborough Project Page, or contract Airport Management at 705-743-6708.