Anticipated Start Date: May 2026
Anticipated End Date: Fall 2027
Status Update:
The Contractor will be implementing the next stage of traffic control associated with the Lansdowne Street West Reconstruction project beginning Monday, September 28, 2026, pending that weather delays are not encountered. The approved road occupancy permit is in effect through October 30, 2026.
During this stage, the following turn restrictions will be in place at the Lansdowne Street West/Kawartha Heights Boulevard/Spillsbury Drive intersection:
- Southbound Kawartha Heights Boulevard: no through or left-turn movements; traffic will be required to turn right onto westbound Lansdowne Street West.
- Northbound Spillsbury Drive: no through or left-turn movements; traffic will be required to turn right onto eastbound Lansdowne Street West.
- Lansdowne Street West: left turns onto Kawartha Heights Boulevard and Spillsbury Drive will be restricted.
Posted detour routes will direct affected traffic around the intersection, which are included alongside the attached traffic staging plans provided to assist with school access and transportation planning.
Traffic will continue to be maintained along Lansdowne Street West; however, motorists should expect localized restrictions and minor delays while the work is underway.
The primary focus of the 2026 work is the installation of a new watermain at the intersection, while the full reconstruction of the intersection is currently scheduled for 2027.
The City of Peterborough awarded the above noted project to Dufferin Construction Company
Scope of work:
The scope of work generally includes; replacements of storm sewers, sanitary sewers, watermain, concrete curb and gutter, concrete sidewalk, road granular base and the asphalt road structure, traffic signals, streetlights, landscaping, tree plantings, pavement markings, installation of multi-use trails, and regulatory signage as part of a full scope road reconstruction. The reconstruction will also include upgrades to the Spillsbury Drive, Kawartha Heights Boulevard and Lansdowne Street West intersections, and the installation of new traffic signals at Lansdowne Street West and Village Crescent.
Lane Reductions and Traffic Impacts:
To facilitate these works the Contractor will be reducing Lansdowne Street West two lanes, one dedicated eastbound lane and one westbound lane. To accommodate work on Spillsbury Drive and Kawartha Heights Boulevard, traffic will be reduced to two lanes, with one dedicated lane maintained in each direction (northbound and southbound).
Access for local traffic and businesses will be maintained at all times during traffic flagging operations, lane shifts, lane reductions, etc. It is expected that local traffic may experience delays within the construction limits.
Project Contact:
Any issues or questions that arise prior to and/or during construction, please contact the following:
Todd Williamson
Construction Inspection Technologist III
Cell: (705) 930-6864